Pictorial record of progress

16th July 2025 - Day 18 - Our raft foundation gets poured

21st July 2025 - Day 19 - With rain and without shuttering

9th July - Day 17 - Shuttering in place ready for concrete

3rd July - Day 13 - Steelwork on top of DPM

24th June 2025 - Day 7 - Below ground services / ducting in place - stone layers being built up

20th June 2025 - Day 5 - First layer of stone sub-base

19th June 2025 - Day 4 - Sub-foundation service ducting and soil pipes go in

18 June 2025 - Day 3 - we can now clearly see the house outline

17 June 2025 - Day 2 - things move quickly!

16th June 2025 - Day 1 - we break ground

27th May 2025 - SIPs being made

9th Jan 2025 - Geotechnical investigations